DATE

DAILY NOTES

12/15-12/21
Demo fire unit
12/27
Denailing and chipping up tile
Jan - Feb
Remodeled bathroom
March
Permits were approved
4/3
Frame work
4/5-4/19
Rough HVAC
4/26-5/2
Brought closet in masterbedroom up to code
5/4-5/14
Roughed in electrical for fire unit
5/24-6/5
File in review RE: city violations
6/8
Framework being complete for inspection

6/15

Installing windows

6/22-6/23

Stock Drywall

6/24-6/26

Hang, Tape, & Finish Drywall

07/05

Roy met with H/O to discuss paint samples.

07/07

John to deliver samples that are beige or stone color.

07/07

Roy spoke with homeowner, in regards to what is remaining at job.

DATE
TASK
COMPLETE
 
Demo
X
 
Structural
X
 
AC
Rough
 
Plumbing

Rough

6/22/06
Insulation & Drywall

X

 
Carpentry
 
 
Painting
 
 
Fence
 

Do you have questions for your foremen? Feel free to fill out the form below and we will be more than happy to assist you.

Full name:
Email address:
Questions or Comments:
  

Payments
Date
Paid
1st Draw
11/28/05
PAID
2nd Draw
Requested. Waiting on Chase's Inspection.

PENDING

Extras
2/6/06

PENDING

3rd Draw (upon completion)

   

This Week's Schedule
Monday
Project Clean up
Tuesday
Finish removing tin set from floor
Wednesday
 
Thursday
 
Friday
 

Date
      Inspection
Pass
04/19
Rough AC
             X
05/24

Rough Electrical

              X
06/09
Framing Inspection
              X

     06/28

Drywall & Screw

X